Our role

Ashfold was appointed in April 2015, to implement the construction design management, after a competitive selection process. This involved the development of the design and the subsequent choice of contractors to carry out the installation. In this capacity Ashfold has managed the appointment of the architect and other specialist designers. It has developed a strategic masterplan programme and agreed a budget for both the construction and the client’s furniture and IT budget.

Project details

The development of the Category B fit out for a 10,000 sqft head office for a private client.

The Heals Building is a Grade 2 listed building with many existing historic features. The design has been developed by architect Cove Burgess to recognise these original features but also accommodate the client’s exacting brief.

Lunch-Area-2_400x300

Related Projects

  • Working
    Working

    10 Aldersgate Street

    >
  • Working
    Working

    192 Sloane Street

    >
  • Working
    Working

    Direct Marketing Association

    >
  • Working
    Working

    Elsley House

    >

Statistics

  • Project Budget – £1 Million
  • Accommodation – Category B fit out including meeting rooms, furniture, IT, security, specialist lighting etc
  • Programme Completion – January 2016

Appointment

Project Management