11 Pilgrim St, The Carter – Progress Update

We recently managed to get back out on site to take a recording of progress on ‘The Carter‘. The new name for the project we’re working on at 11 Pilgrim St. After over a year on-site, the project is really starting to take shape. The filling-in of the former atrium is fully complete. The timber for the new floor has arrived and the frame is being constructed. The contracting team is now starting to work in earnest on the fit-out of the newly refurbished floors 1-6.

The newly refurbished Carter building incorporates some outstanding circular economy and sustainable practices. These include the reuse of floor tiles, retention of substantial amounts of the original building, and retrofitting. The new building also features the timber/steel new floor and a number of green walls and increased access to balconies and outdoor space for incoming tenants.